57 / 62 · 22 Test Strategy & Quality Metrics · Quality Trends and Forecasting← prev⊞ allnext →☰ Read as one page
7.5Burndown Charts for Bug Resolution
The Bug Burndown
A bug burndown shows the remaining open bugs over time, tracking whether the team is closing bugs fast enough to meet the release date.
Open Bugs Remaining
25 │ ●
20 │ ● Ideal burndown (dashed)
│ - - ● - - -
15 │ ● - - -
│ ● - - -
10 │ ● - - -
│ ● - - -
5 │ ● - - -
│ ● ─ ─ ● (actual stalls here)
0 │──────────────────────────────────→ Release Date
D1 D3 D5 D7 D9 D11 D13 D15
Reading the Burndown
| Pattern | Meaning | Action |
|---|---|---|
| Actual tracks ideal | On track to close all bugs by release | Continue current pace |
| Actual above ideal (falling behind) | Closing bugs slower than planned | Add resources, deprioritize low-severity bugs, or extend timeline |
| Actual below ideal (ahead) | Closing bugs faster than planned | Good position; use extra time for exploratory testing |
| Actual flattens (plateau) | Bug closure has stalled | Investigate blockers: are fixes waiting for review? Environment issues? |
| New bugs added (burndown goes up) | Testing is still finding new bugs faster than fixes are closing them | Too much scope; prioritize ruthlessly |
Bug Burndown Formula
Expected Bugs Remaining on Day D = Total Open Bugs x (1 - D / Total Days)
Example:
Start: 25 open bugs, 15 days to release
Day 5 expected: 25 x (1 - 5/15) = 25 x 0.667 = 16.7 bugs
Day 5 actual: 19 bugs
Status: Behind (19 > 16.7). Need to increase fix rate by 14%.